Double girder gantry crane 45 + 45 tons for the “trillion billion VND” category
To speed up the progress of Nhon – Hanoi Station, ensure it will be put into operation in April 2021 and solve the problem above. The Hyundai-Gella contractor complex and the underground tunnel construction contractor FECON have developed a plan and decided to use a 45 + 45-ton double-beam gantry crane to transport materials and equipment of TBM tunneling machines and soil and rock layer. They dug out of the tunnel at Station S9.
After carefully studying construction options, solutions, and technologies, Hyundai-Gella Contractors and underground tunnel construction contractor FECON decided to award the contract to provide the 45 + 45 ton Double Girder Gantry Crane for VINALIFT.
SPECIFICATIONS:
DEVICE TYPE | DOUBLE-GIRDER GANTRY CRANE |
LOAD | 90-TON |
NUMBER OF HOISTS | 45 TON x 2 |
WORKING MODE | FEM 4M |
SPAN | (23+4)M |
LIFTING HEIGHT ABOVE RAIL | 10M |
PIT DEPTH | 16M |
LIFTING SPEED UNDER LOAD | 9M/MIN |
LIFTING SPEED WITHOUT LOAD | 18M/MIN |
TROLLEY TRAVELING SPEED | 20M/MIN |
GANTRY CRANE TRAVELING SPEED | 20M/MIN |
LOADING/UNLOADING CAPACITY | 500 TON/H |
TOTAL INSTALLED POWER | 265KW |
In addition, the same project also has a 15-ton double-girder gantry crane serving to bring precast concrete sections to the tunnel for assembly.
Thank you for reading this article. Please follow us on our WEBSITE or social media platforms such as FACEBOOK, LINKEDIN, and YOUTUBE for new articles with useful information.
In addition, you can add the following information in similar articles: (30+30) Ton Gantry Crane, 100-Ton Gantry Crane